Proposed Data Center Information
Iron County is providing this page as a central location for public information related to proposed data center projects.
Information and documents will be updated as they become available. Members of the public are encouraged to review the materials and participate in the public meeting process when applicable.
180-Day Moratorium
On May 26, 2026, the Iron County Commission adopted an ordinance establishing a 180-day moratorium on the acceptance and processing of new land use applications related to data centers, data center power plants, and solar power plants.
View Moratorium OrdinanceCurrent Applications
Antelope Data Center
Scheduled for Planning Commission review
This item is scheduled for the June 4, 2026 Planning Commission meeting at 5:30 p.m. at Festival Hall. There will not be a public hearing.
Red Butte Data Center
Application on hold
The Red Butte Data Center application was submitted on May 4, 2026, and was deemed incomplete on May 22, 2026. The project is subject to the 180-day moratorium, so the application is not currently in process and is on hold until after the moratorium ends.
Documents
Public Meetings and Updates
Public meeting information, agendas, and related updates may be posted on the Planning Commission meeting page as items are scheduled.
View Planning Commission Information